SPECIFIC INSTALLATION DETAILS SUPRA CITADIN 180 COLUMN Erecting a column You can build a column with Supra Citadin 180 corner blocks.
Step 1 Measure the spot where the column will be built. Each column has an approximately 26½ in. x 26½ in. (673 mm x 673 mm) cross-section.
Step 2 Fill a 29 in. x 29 in. (737 mm x 737 mm) base that is 6 inches (150 mm) deep with 0-3/4 in. (0-20 mm) granular material. Compact well (use a vibrating plate, a vibrating roller or a jumping jack type of rammer. Step 3 Installing the first row Lay out the first row of blocks as shown in Layout 1. Fit them snuggly, check the level and use a right angle to ensure a 90°angle. Use concrete adhesive to set the subsequent rows.
Layout 1
Layout 2
Installing the second row Proceed as for the first row, but according to Layout 2. Installing the subsequent rows Do as above, going back to Layout 1 and continue alternating layouts with each new row.
Step 4 Citadin 90 coping
Install the Citadin 90 coping on the top of the column (see Figure 1). For greater stability, glue the Citadin 90 coping with a concrete adhesive.
Figure 1