Installation guide - 26
WALLSTONES, COLUMNS AND STEPS
SPECIFIC INSTALLATION DETAILS SUPRA CITADIN 180 BLOCK (CONTINUED) 10. Backfill Placement and Compaction
Spread the drainage backfill, typically 20 mm clean stone, behind the wall face as specified in the plans (at least 30 cm). Finer material must not be used as drainage backfill. Behind the drainage backfill, use a backfill material that meets the project specifications. When spreading backfill over the geogrid, place the backfill so as to eliminate slack in the geogrid. Spreading backfill from the wall face or parallel to the wall face will help minimize geogrid slack. In addition to spreading backfill in the indicated direction, a pitchfork can be used at the geogrid ends to remove waves or slack during spreading.
11. Corner To form a 90° angle for the coping, we recommend using two coping modules cut to a 45° angle and always begin installation with the corner, as illustrated.
45 o
Cutting line
12. Finishing Once the last row of modules is installed, cover the clear stone behind the wall with a geotextile membrane to avoid contamination from the draining mass. Fill behind the last row of blocks and the coping with nearby soil or other materials (earth, plant matter, mulch, etc.). Level the work in order to complete the layout.
Volume 26 BOLDUC Installation Guide - 33